Aercon AAC Logo  
HomeLatest NewsProductsAercon FloridaAercon IndustriesContact
 

An AERCON block wall will usually consist of a variety of AERCON products, integrated together to create a complete wall system that satisfies the project requirements. The installation process is basically the same regardless of the individual components. Blocks are typically installed directly on a foundation system, but can also be installed on an elevated floor for multi-story construction. In both conditions, the initial bed joint is a critical element. The base mortar joint must be level and true so that the construction can proceed with minimal adjustments. In order to provide adequate thickness for adjustment, the initial bed joint is usually Type M or S mortar, 3/8 to 1/2 inch in thickness. Head joints in the starter course are mortared together with AERCON thin bed mortar. When thin bed mortar is used at a joint, it is to be applied with a trowel having the proper style, teeth and width to ensure coverage across the entire thickness of each block.

Lay successive courses plumb, level, and true to line, in running bond with 8-inch lap (6-inch minimum) for standard blocks; when cored block is used, lap should equal the block thickness, in order to align the cores at the corners. Use thin bed mortar at all bed joints and for head joints of flat face blocks. Tongue and groove blocks do not require mortar at the head joints. Check each block as laid for levelness and plumbness, making adjustments as required using a rubber mallet, while the mortar is still soft and plastic.

Vertical Block Install

Thin bed mortar should be applied with a trowel having the proper style, teeth and width to ensure adequate coverage.

When necessary to accommodate an odd dimension or configuration, blocks are to be cut with an appropriate hand saw or band saw that is specially designed for cutting autoclaved aerated concrete (AAC). Consider the layout of the wall before starting construction and install blocks in a manner that minimizes cutting. Provide temporary bracing as required.

Cored blocks are used at specified locations to provide a continuous cell for a threaded rod or a reinforcing bar. If a threaded rod is used to resist overturning of a shear wall or to resist direct uplift from a roof, the cell does not require grouting since the rod is strictly a tension element that can be tightened to achieve tautness for load transfer. If a reinforcing bar is used, then the cell must be grouted to ensure the rigidity of the bar during load application and to provide a lap splice when necessary. A reinforcing bar in a grouted cell can function as a tie-down in addition to increasing the flexural strength of the wall. A fine aggregate grout, with good flowability, should be used to fill the cells. The cells should be wetted prior to filling, and a vibrator should be used during the filling process. Cored block are installed in the same manner as standard block. At the base course, if a clean-out or inspection port is required, the cored block can be cut so that the core becomes exposed to one side. If necessary, repair mortar can be used to fill and seal the base course block where it was cut.

Filled U-blocks can be used as bond beam elements and as lintels. The U-shape is manufactured from standard blocks, which ensures dimensional and material compatibility with other types of AERCON blocks and panels. U-blocks are installed using thin bed mortar for the bed joint and head joints. Typically two reinforcing bars are inserted in the U-shaped cavity, one above the other (not side-by-side). The U-blocks are then filled with a small aggregate concrete mix to complete the Ublock installation. Prior to pouring the concrete, the cavity should be wetted to minimize the absorption of water from the poured concrete.

Solid, reinforced AERCON lintels are installed in the same manner as standard blocks – mortaring the bearing bed joints and the head joints with thin bed mortar. Depending on the height of the opening that the lintel spans across, a filler piece of block may be required to achieve the desired bearing elevation; or the blocks that support the lintel can be notched downward if the coursing results in the bearing elevation being too high. Based on their internal reinforcing, AERCON lintels are intended to be installed in a particular orientation and are marked to indicate that orientation. AERCON lintels are not to be cut unless authorized by an AERCON Representative.

The large size of ValuBlocks enables more wall area to be installed per block, expediting installation, minimizing the number of blocks that are handled and minimizing the volume of mortar that is needed. Depending on the size and weight of the ValuBlocks, a minicrane and special lifting clamp may be required to lift and set the blocks accurately. Use thin bed mortar at all bed joints and for head joints of flat face blocks. Tongue and groove blocks do not require mortar at the head joints. ValuBlocks can be manufactured with cores and/or radiused edges. When two radiused edge blocks are installed adjacent to each other, a cell is created, dimensionally the same as the drilled cores.

Multiple configurations for interfacing reinforcing bars and tiedowns at the foundation are available. Some are shown in the Construction Details Section. These include epoxying into the foundation to ensure accurate placement, casting in a hooked anchor, and using an embedded composite system.

 
 

**Refer to chart for Dimensions and Strength Classes

Roof

- Assembly and Erection
- Structural Design
- Construction

Floor

- Assembly and Erection
- Structural Design
- Construction

Horizontal

- Assembly and Erection
- Structural Design
- Construction

Vertical

- Assembly and Erection
- Structural Design
- Construction

Interior

- Construction

Lintel and Blocks

- Assembly and Erection
- Structural Design
- Construction